It should follow the power from the LV switchboard to everything that turns aggregate and bitumen into hot mix: cold feed bins and conveyors, the drum dryer drive and burner controls, the exhaust fan and baghouse, the hot elevator and screens, the mixer, hot storage silos and loadout, and the bitumen tank heating. It is all imaged live while the plant is producing, with process heat ruled out before anything is reported.
Survey while the plant is producing
An asphalt plant’s electrical load follows production. The dryer drum, exhaust fan, elevators and mixer carry their working current only while mix is being made, and output rises and falls with orders and the season. Thermography only shows a weak connection while current is flowing through it, so the survey is booked on a normal production day, not during a shutdown or a quiet winter week. The report records what was running when each panel was imaged.
What the scope should include
- LV distribution: the main LV switchboard and outgoing feeders to the plant, the bitumen tank farm, the control cabin and site services.
- Motor control: MCCs and VSDs for cold feed bins, collecting and slinger conveyors, the dryer drum drive, exhaust fan, hot elevator, screens and mixer (see MCCs and VSDs imaged while running).
- Burner and dryer: burner management and fuel pump panels and the combustion air fan supply.
- Dust collection: baghouse fan, pulse-cleaning controls, screw conveyors and filler handling.
- Bitumen system: tank heating panels (electric elements or thermal oil heaters), bitumen pump starters and the supplies to heated lines.
- Storage and loadout: skip hoist or drag conveyor drives, hot storage silo gates and heating, and the weighbridge and loadout controls.
- Compressed air: the compressor plant that runs gates, dampers and baghouse cleaning.
The survey covers electrical panels and connections. Burner servicing, dryer drum refractory, tank inspection and mechanical checks are separate jobs. If the site also runs a quarry, the quarry and aggregates page covers the crushing and screening side.
Traps a good thermographer avoids
- Process heat. The dryer drum, hot elevator, mixer and bitumen pipework are hot by design, and panels close to them can read warm all over. That is not a finding. What matters is the difference in °C between matching connections, phase to phase, on the same circuit.
- Heated tanks and lines. Bitumen tank heaters and heated pipework are meant to run warm. The thermographer checks the connections in their supply panels, not the heat they are supposed to produce.
- Cycling loads. The mixer, skip hoist and silo gates work in batches. Their panels are imaged across several cycles so each one is seen working.
- Dust and reflections. Dust on enclosures changes how surfaces read, and bare metal reflects heat, so the thermographer changes angle to confirm a hot spot belongs to the connection.
- Anti-condensation heaters. Panel heaters warm the enclosure, not the connection, and are not reported as findings.
Working on an asphalt plant
The thermographer follows the site induction and PPE rules, keeps clear of loading lorries and the loadout lane, and works with the plant operator so panels near moving plant are reached safely. Panels are opened by the site’s electrician under the site’s own permit system (see who opens the panels). Production carries on as normal.
What the report gives you
A same-day report that locates each finding by panel, circuit and phase, with a thermal and visual image pair, the measured temperature, where it was taken, the difference in °C from the matching reference and the running state at the time. Areas that could not be imaged safely are listed. Ti inspects and reports. The site’s electrical team or contractor investigates any finding with the equipment isolated.
Why load matters
Load is what makes a weak connection show. On a London data centre build, commissioning thermography by our team found 16 busbar sections reading above 80 °C under test load, the highest 103.5 °C at a tap-off unit. On an asphalt plant that means imaging the drives and heaters while mix is being made, not on a quiet day.
Frequently asked questions
Does the plant have to stop for the survey?
No. Thermography images energised equipment on load, so the survey is done while the plant is producing. A stop is the worst time to survey because the drives are not carrying their working current.
When in the year is best?
During the main production season, when the dryer, mixer and bitumen system are working at normal output. Many sites book it before the busy season so findings can be dealt with in good time.
Is the bitumen tank farm included?
Yes, the tank heating panels, pump starters and their supplies are part of the electrical scope. The tanks themselves are not inspected.
Related reading
- Data centre electrical thermography
- Busbar thermography at commissioning
- Switchgear thermography
- Annual PPM electrical thermography
- 7 electrical risks thermography finds
Ti Thermal Imaging’s surveys are carried out by ITC Level 3 thermographers, and Ti is a Level 3 certified company. Our work has featured on BBC News and ITV.
Talk to us: +44 20 3885 7464 · sales@thermalimaging.co.uk · contact page
About the author: Rachael Browning, General Manager, Ti Thermal Imaging.